+92 300 6753414 info@fgoc.com.pk Mon – Sat, 9:00 – 18:00
Future Engineering (Pvt) Limited logo

Future Engineering (Pvt) Limited

Engineering, HVAC, project management and services for energy and industrial assets

Overview

About Future Engineering

Future Engineering (Pvt) Limited is the engineering arm of the group and the company most of our clients deal with first. It takes a requirement from the earliest sketch through detailed design, procurement, construction and commissioning, and hands back a working asset.

The company works across infrastructure, manufacturing and energy, designing and maintaining the kind of complex systems where mechanical, electrical, civil and control disciplines all have to line up. That coordination is the real job, and it is what the company is built around.

Because the wider group also manufactures, fabricates and moves cargo, Future Engineering can carry a project end to end without handing the difficult parts to a chain of subcontractors. Clients get one team, one programme and one point of accountability.

Talk to This Company
Future Engineering (Pvt) Limited
Capabilities

What Future Engineering Does

01

Design & Engineering

Concept studies, detailed design, drawings and specifications across mechanical, electrical, civil and control disciplines.

02

EPC Delivery

Full engineering, procurement and construction packages under a single contract, with one team accountable for the programme.

03

Electro-Mechanical Installation

Erection of rotating equipment, piping, cabling, switchgear and instrumentation, through to loop checks and energisation.

04

Civil & Structural Works

Foundations, structures, buildings and site works built to project specification and industrial safety standards.

05

Commissioning & Handover

Pre-commissioning checks, functional testing, performance runs and a documented handover the operating team can actually use.

06

Operations & Maintenance Support

Planned maintenance, outage support and technical assistance that keeps the asset performing after handover.

Why Work With Us

What you get

  • One accountable partner from first drawing to final handover
  • Mechanical, electrical, civil and control work coordinated by a single team
  • In-house fabrication and logistics through the wider group
  • Crews that can be mobilised quickly for outages and time-critical work
  • Documentation and testing records handed over in a usable state
Sectors Served

Where we work

Power GenerationOil & GasIndustrial PlantsWater & UtilitiesInfrastructureRenewables
Track Record

Projects We Have Worked On

747 MW CCPP Thermal Power Project2010 – 2014
Future Engineering (Pvt) Ltd

747 MW CCPP Thermal Power Project

Guddu, SindhClient: Harbin Electric International (HEI), China

  • Installation & commissioning of networking and communication systems at HEI site offices and living camps
  • Supply of electrical & mechanical materials
  • Supply of accommodation material for HEI camps
  • Transportation services
747 MW CCPP Power Plant — Material & Machinery Supply2010 – 2014
Future Engineering (Pvt) Ltd & FEPL Engineering Works (Pvt) Ltd

747 MW CCPP Power Plant — Material & Machinery Supply

Guddu, SindhClient: Tianjin Electric Power Construction Co. (TEPC), China

  • Project material & rental machinery supplier for E&M erection
  • Cranes and DG sets on rental / purchase; air compressors for sand blasting
  • Fabrication services from the FEPL Engineering workshop
  • Heavy-duty steel wire ropes, fibre cloth and consumables
667 Natural Gas Treatment Plant — KPD-TAY Integrated Development Project, Phase-II2014 – 2015
Future Engineering (Pvt) Ltd

667 Natural Gas Treatment Plant — KPD-TAY Integrated Development Project, Phase-II

Tando Jam, SindhClient: Shandong Kerui Petroleum Equipment Co. Ltd (Kerui Group), China

  • Technical manpower for vessels, power plant and boiler installation & commissioning
  • Tank fabrication
  • Manpower for E&M erection, October 2014 – November 2015
  • Peak manpower of 1,618 persons in June 2015
Pakistan NRL ISBL Upgradation Project — Diesel De-sulphurisation Unit & Naphtha Isomerisation2015 – 2017
Future Engineering (Pvt) Ltd

Pakistan NRL ISBL Upgradation Project — Diesel De-sulphurisation Unit & Naphtha Isomerisation

National Refinery Ltd, KarachiClient: 7th Construction Company of CNCEC (CC-7), China

  • Skilled and unskilled manpower for civil, mechanical and electrical works
  • November 2015 – August 2017
2 × 660 MW Coal-Fired Power Project2017 – 2020
Future Engineering (Pvt) Ltd

2 × 660 MW Coal-Fired Power Project

Hub, BalochistanClient: Energy China (CEEC)

  • Skilled and unskilled manpower for civil, mechanical and electrical works
  • January 2017 – February 2020
MCR Revamp Project, Package-2 — PARCO Refinery2018 – 2019
Future Engineering (Pvt) Ltd

MCR Revamp Project, Package-2 — PARCO Refinery

Qasba Gujrat, MuzaffargarhClient: Hualu Engineering & Technology Co. Ltd, China

  • Skilled and unskilled manpower for civil, mechanical and electrical works
  • September 2018 – December 2019
NRL MCR Revamp Project2019 – 2020
Future Engineering (Pvt) Ltd

NRL MCR Revamp Project

National Refinery Ltd, KarachiClient: 6th Construction Company of CNCEC (SCC-CNCEC), China

  • Skilled and unskilled manpower for civil, mechanical and electrical works
  • August 2019 – March 2020
Engro Polymer & Chemicals2019 – 2020
Future Engineering (Pvt) Ltd

Engro Polymer & Chemicals

KarachiClient: 6th Construction Company of CNCEC (SCC-CNCEC), China

  • Skilled and unskilled manpower for civil, mechanical and electrical works
  • November 2019 – February 2020
How We Work

Working With Future Engineering

Four stages, and one team accountable for all of them.

Define

Requirement, site survey and feasibility — agreeing what the asset has to do before anything is drawn.

Design

Detailed engineering across mechanical, electrical, civil and control, reviewed for constructability.

Build

Procurement, construction and installation, with FEPL Engineering Works fabricating and Future Logistics delivering.

Commission & Support

Testing, start-up and handover, followed by maintenance and outage support for the life of the asset.

Common Questions

Questions Clients Ask Future Engineering

Can you take on only part of a project?
Yes. Many clients engage us for a single package — a design review, the electro-mechanical installation or commissioning — rather than full EPC. The scope is agreed in writing before work starts.
How are changes handled once work has started?
Changes are priced and agreed in writing before the extra work is done, so scope, cost and programme stay clear for both sides. Variations agreed on site and never recorded are one of the most common causes of project disputes.
Do you work only on new plant?
No. A large share of the work is on existing plant — outages, rehabilitation, control system upgrades and modifications, often planned around a unit that has to stay in service.
The Group

Other Companies in the Group

Have a project in mind?

Tell us what you need and our team will come back to you with a practical, costed way forward.

Talk to Our Team